A shallow trench for a 1,000-foot waterline installation will take 10 days. It will take 4 days to install the first 400 feet of pipe. A water meter will then be installed during the following 2 days at the end of the pipe. After the meter is installed, the remaining 600 feet of pipe will be installed in 6 days. Develop a linear schedule for this project.
1. A project consists of replacing the track on an existing railroad line, involving 3,000 feet of track. The old track can be removed at a rate of 70 feet per hour. The old rail- road ties can be removed at a rate of 200 feet (measured along the track) per hour. The new ties […]