What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Is the project ahead of schedule or behind schedule? Is the project under budget or over budget?

Resource Allocation And Risk Management
Part 1
Review the “Project Execution” section of Chapter 3 in the textbook. Follow the steps provided to guide your baseline process and the subsequent status of you plan.
Open the Microsoft Project “Global Treps Project Rev4” file and set a baseline. To set the baseline, first select the project tab.
Then select set baseline. Then click OK.
Turn on the Tracking Table.
Update the following tasks with the revised actuals specified below.
Update the Resource Sheet to reflect the revised labor costs specified below.
Save the Microsoft Project file as “Global Treps Project Rev5.”
Revised Actuals:
Finalize project team – 100% complete
Develop project charter – 100% complete
Develop scope statement – 100% complete
Develop and refine other plans – 100% complete
Evaluate current systems – 100% complete – Make the “Actual Start” date the “Current Date” and the “Actual Finish” date 10 days later than the “Current Date.”
Conduct research for income mechanism into Global Treps – 30 days – 100% complete
Evaluate current system – 10 days – 100% complete
Define requirement – 22 days – 100% complete
Define user requirements – 23 days – 100% complete
Define content requirements – 29 days – 100% complete
Define system requirements – 33 days – 100% complete
Define server owner requirements – 20 days – 100% complete
Define specific functionality – 33 days – 100% complete
Define risks and risk management approach – 21 days – 100% complete
Develop project plan – 32 days – 100% complete
Brief web development team – 3 days – 100% complete
Revised Resource Labor Costs:
Project Manager (you): $120 per hour
Website Developer (Bobby): $125 per hour
System Test Engineer and Event Runner: Vietnam (Kim): $55 per hour
Support Team Manager and Event Runner: India (Ashok): $55 per hour
Event Runner: Ethiopia (Alfreda): $55 per hour
Part 2
Using the information from “Global Treps Project Rev5,” you must evaluate the seriousness of the threats to project success based upon data from the Earned Value Table and Earned Value Report. Complete the steps below to access the data.
Using the “Global Treps Project Rev5” you created in Part 1, view the Earned Value table by selecting the “Select All” button, then right-click your selection, select “More Tables,” and double-click on “Earned Value.” Reveal all the columns. Be sure the entire number shows in each column. Add a column for the cost performance index (CPI) and schedule performance index (SPI).
View the earned value report by clicking the “Report” tab, and then click “Costs” followed by the “Earned Value Report.”
Create a Word document and insert a screen shot of the earned value table and the earned value report.
Using the earned value table and the earned value report, answer the following questions in the Word document after the screenshots.
Questions:
What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
Is the project ahead of schedule or behind schedule? Is the project under budget or over budget?
Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
Use the SPI to estimate how long it will take to finish this project.
Part 3
Create a management report to discuss where the project stands in terms of the triple constraint: meeting scope, time, and cost goals at a specific point in time. Use the revised information from the Microsoft Project earned value dashboards and reports to communicate the project status to project stakeholders. Be sure the comments address each of the questions below and provide any additional information required in the template.
Are there issues that need to be escalated?
Is it acceptable to do nothing and simply proceed?
Should the project be terminated?
Based on your evaluation of the threats to the project, how should you proceed?

© 2020 EssayQuoll.com. All Rights Reserved. | Disclaimer: For assistance purposes only. These custom papers should be used with proper reference.